题名

陸上風力發電機組興建工程受風不確定性因素影響之工期預測模式

并列篇名

SCHEDULE PLANNING MODEL FOR ONSHORE WIND TURBINE CONSTRUCTION PROJECT SUBJECTED TO THE IMPACT OF WIND

DOI

10.6652/JoCICHE.201706_29(2).0005

作者

郭斯傑(Sy-Jye Guo);陳榮興(Jung-Hsing Chen);丘佳欣(Chia-Hsin Chiu)

关键词

陸上風力發電機組 ; 風不確定性因素 ; 工期預測模式 ; 生產力 ; wind turbine construction ; impact of wind ; schedule planning model

期刊名称

中國土木水利工程學刊

卷期/出版年月

29卷2期(2017 / 06 / 01)

页次

109 - 117

内容语文

繁體中文

中文摘要

風力發電具備低污染及低成本之優點,為具潛力的再生能源之一,且台灣風力資源充沛,故風力發電機組興建工程將在台灣積極開發推動。目前工程界實務上對於受天候影響之工期預估大多是根據經驗法則以概估方式處理。本研究引用陸上風力發電機組興建工程工址區域之歷史風速資料,藉由分析各級風對各受風敏感之作業項目的直接生產力影響,再結合經模糊隸屬函數量化處理之專家經驗,建立一受風影響之工期預測模式,並以「桃園蘆竹風力發電機組興建工程」為例,測試此工期預測模式之成效,期能提供排程人員更為可靠之工期預測與排程參考。

英文摘要

Because of its characteristics of low pollution and low cost, wind energy becomes one of the most promising renewable energy. With plentiful of wind energy, Taiwan is highly interested in establishing wind farms for sustainable green energy developments. However, wind could produce adverse impacts on some wind-sensitive tasks during constructing wind turbine projects. This research presents a schedule planning model for wind turbine construction project subjected to the impact of wind. Through the support of professional expertise, the employment of fuzzy membership functions, and the application of historical wind speed data, the productivity loss (PL) subjected to various Beaufort scale of wind can be analyzed and the duration can be simulated and forecasted by the model. Besides, an actual wind turbine construction project is used to demonstrate the practicality of the model. The findings from this research are very helpful in schedule planning for wind turbine construction projects subjected to the impact of wind.

主题分类 工程學 > 土木與建築工程
工程學 > 水利工程
工程學 > 市政與環境工程
参考文献
  1. (2012).Manual on Marine Meteorological Services-Volume 1: Global Aspects.World Meteorological Organization.
  2. Apipattanavis, S.,Sabol, K.,Molenaar, K. R.,Rajagopalan, B.,Xi, Y.,Blackard, B.,Patil, S.(2010).Integrated framework for quantifying and predicting weather-related highway construction delays.Journal of Construction Engineering and Management, ASCE,136(11),1160-1168.
  3. Ayyub, B. M.,Halder, A.(1984).Project scheduling using fuzzy set concepts.Journal of Construction Engineering and Management, ASCE,110(2),189-204.
  4. Bataineh, K. M.,Dalalah, D.(2013).Assessment of wind energy potential for selected areas in Jordan.Renewable Energy,59,75-81.
  5. Bhandari, B.,Lee, K. T.,Lee, G. Y.,Cho, Y. M.,Ahn, S. H.(2015).Optimization of hybrid renewable energy power system: A review.International Journal of Precision Engineering and Manufacturing Green Technology,2(1),99-112.
  6. Borowy, B. S.,Salameh, Z. M.(1996).Methodology for optimally sizing the combination of a battery bank and PV array in a wind/PV hybrid system.IEEE Transactions on Energy Conversion,11(2),367-375.
  7. Chao, L. C.,Hsiao, C. S.(2012).Fuzzy model for predicting project performance based on procurement experiences.Automation in Construction,28,71-81.
  8. El-Rayes, K.,Moselhi, O.(2001).Impact of rainfall on the productivity of highway construction.Journal of Construction Engineering and Management, ASCE,127(2),125-131.
  9. Guo, S. J.(2000).Computer-aided project duration forecasting subjected to the impact of rain.Journal of Computer-Aided Civil and Infrastructure Engineering,15(1),67-74.
  10. Gupta, R. A.,Kumar, R.,Bansal, A. K.(2015).BBO-based small autonomous hybrid power system optimization incorporating wind speed and solar radiation forecasting.Renewable and Sustainable Energy Reviews,41,1366-1375.
  11. Jeong, H. S.,Atreya, S.,Oberlender, G. D.,Chung, B. Y.(2009).Automated contract time determination system for highway projects.Automation in Construction,18(7),957-965.
  12. Justus, C. G.,Mikhail, A.(1976).Height variation of wind speed and wind distributions statistics.Geophysical Research Letters,3(5),261-264.
  13. Katinas, V.,Sankauskas, D.,Markevicius, A.,Perednis, E.(2014).Investigation of the wind energy characteristics and power generation in Lithuania.Renewable Energy,66,299-304.
  14. Khamooshi, H.,Golafshani, H.(2014).EDM: Earned duration management, a new approach to schedule performance management and measurement.International Journal of Project Management,32(6),1019-1041.
  15. Koehn, E.,Brown, G.(1985).Climatic effects on construction.Journal of Construction Engineering and Management, ASCE,111(2),129-137.
  16. Korman, R.,Setzer, S. W.,Powers, M. B.(1992).Rains Wreck Summer Schedules.Engineering News Record, McGraw-Hill Construction Weekly,August, 31,6-7.
  17. Lorterapong, P.,Moselhi, O.(1996).Project-network analysis using fuzzy sets theory.Journal of Construction Engineering and Management, ASCE,122(4),308-318.
  18. Mirahadi, F.,Zayed, T.(2016).Simulation-based construction productivity forecast using neural-network-driven fuzzy reasoning.Automation in Construction,65,102-115.
  19. Mohandes, M.,Rehman, S.,Rahman, S. M.(2011).Estimation of wind speed profile using adaptive neuro-fuzzy inference system (ANFIS).Applied Energy,88(11),4024-4032.
  20. Moselhi, O.,Gong, D.,El-Rayes, K.(1997).Estimating weather impact on the duration of construction activities.Canadian Journal of Civil Engineering,24(3),359-366.
  21. Pan, N. F.(2005).Assessment of productivity and duration of highway construction activities subject to impact of rain.Expert Systems with Applications,28(2),313-326.
  22. Quan, P.,Leephakpreeda, T.(2015).Assessment of wind energy potential for selecting wind turbine: An application to Thailand.Sustainable Energy Technologies and Assessments,11,17-26.
  23. Ritter, M.,Shen, Z.,Cabrera, B. L.,Odening, M.(2015).Designing an index for assessing wind energy potential.Renewable Energy,83,416-424.
  24. Salameh, Z. M.,Safari, I.(1992).Optimum windmill-site matching.IEEE Transactions on Energy Conversion,7(4),669-676.
  25. Smith, G. R.,Hancher, D. E.(1989).Estimating precipitation impacts for scheduling.Journal of Construction Engineering and Management, ASCE,115(4),552-566.
  26. Thomas, H. R.,Yiakoumis, I.(1987).Factor model of construction productivity.Journal of Construction Engineering and Management, ASCE,113(4),623-639.
  27. Zadeh, L. A.(1965).Fuzzy sets.Information and Control,8(3),338-353.
  28. 連日新(2011)。台北,國立台灣大學土木工程學系。
被引用次数
  1. 劉佳欣,陳彥仲,胡太山,林海萍(2020)。論證沙崙智慧綠能科學城與台灣南部地區綠能製造業之產業關聯分析。規劃學報,38(1),45-76。
  2. 劉人豪,曾惠斌,郭斯傑,邱祖賢(2023)。以天候窗模式預測台灣離岸風機安裝工期之研究-以允能雲林離岸風場為例。中國土木水利工程學刊,35(3),319-329。
  3. 潘思錡,賈秉靜,胡太山,林海萍(2019)。綠能產業創新模式之形塑:台灣經驗。建築與規劃學報,20(1),27-44。