题名

監造類型與工時關係之探討

并列篇名

INVESTIGATIONS OF THE RELATIONSHIPS BETWEEN SUPERVISION TYPES AND MAN-HOURS FOR PRIVATE CONSTRUCTION PROJECTS

DOI

10.6652/JoCICHE.202111_33(7).0001

作者

劉為杰(Wei-Chieh Liu);王琨淇(Kun-Chi Wang);王維志(Wei-Chih Wang)

关键词

全程監造 ; 重點監造 ; 監造工時 ; 監造工時分配模式 ; supervision types ; supervision man-hours ; man-hour allocation model

期刊名称

中國土木水利工程學刊

卷期/出版年月

33卷7期(2021 / 11 / 01)

页次

473 - 481

内容语文

繁體中文

中文摘要

本研究首先歸納實務上常見之監造類型與定義,再採用累計工時的概念,推估工程各階段所應分配之監造人力。本研究分為三個部份,第一部份先透過建管制度與監造單位組織釐清監造角色。第二部份綜合探討四種不同監造類型,包括全程監造、重點監造、法定監造以及法定勘驗監造。第三部份將6件工程案例依前述類型進行分類,分析各類型監造工時與工進之對應關係,再根據工程各階段監造業務所佔之比重,建構出監造業務工時在各工程進度之適當範圍。研究結果顯示,此模式除可減少人力過剩的情形外,亦可運用於工時成本之控制與分配管理。

英文摘要

During the execution process of construction projects, supervision units often encounter sudden changes during the progress of construction. However, because general supervision man-hours are usually arranged in a flat manner, and it is normally without a response mechanism, it easily leads to final cost increases or surplus manpower. Using private projects as cases, this study adopts the concept of accumulated man-hours to establish a model that allows man-hours and construction progress to correspond with each other, so as to facilitate instant responses by the supervision units and manage the distribution of man-hour costs effectively. Finally, this research presents a Supervisory Strategy Model for Man-hours. This research is mainly divided into four parts. The first part defines the role of supervision according to laws, contracts, construction management systems and supervision unit organization. The second part divides types of supervision into four categories of continuous supervision, intermittent-inspection supervision, periodic supervision, and statutory-inspection supervision. The third part applies a case analysis to establish the corresponding relationship of the cumulative man-hours of supervision and the cumulative progress of a project, as well as to integrate the relationship between the man-hours and construction progress of the supervision business by merging the characteristics of the project timeline. The fourth part constructs a reasonable and safe strategy model that allows active control of the cumulative input ratio of man-hours, so as to facilitate the reasonable allocation and supervision of the total man-hours.

主题分类 工程學 > 土木與建築工程
工程學 > 水利工程
工程學 > 市政與環境工程
参考文献
  1. 中國土木水利工程學會(2019)。,行政院公共工程委員會。
  2. 王恭賢(2008)。雲林,國立雲林科技大學營建工程系。
  3. 伍勝民(2005)。台中,東海大學法律學系。
  4. 何宗欣(2007)。桃園,國立中央大學土木工程學系在職專班。
  5. 李貞儀(2005)。桃園,國立中央大學營建管理研究所。
  6. 林子晴(2012)。台南,國立成功大學土木工程學系。
  7. 林俊佑(2015)。雲林,國立雲林科技大學企業管理系。
  8. 林家愉(2014)。高雄,國立高雄應用科技大學土木工程與防災科技研究所。
  9. 陳賜豪(2011)。新竹,國立交通大學土木工程學系。
  10. 黃至銓(2004)。台中,朝陽科技大學營建工程系。
  11. 黃源凱(2007)。新竹,國立交通大學工學院工程技術與管理學程。