中文摘要

近年來,網圖評核術(GERT)已廣泛運用在不同領域裡,網圖評核術之作業參數主要取自於決策者主觀意見或專家的經驗判斷,然礙於模式僅能以明確值來描述參數,舞法表達參數的不確定性,進而影響整體規劃。針對上述問題,本文以模糊數來表示作業參數,進而發展一模糊網圖評核術模式。主要步驟如下:(1)根據系統分析繪製網圖評核術網路圖,(2)以三角模糊數表示網圖評核術中的作業參數,(3)運用模糊數的計算代入逐步運算法中,建立模糊網圖評核術模式。本文以一個半導體加工範例進行驗證,說明如何建立模糊網圖評核術模式。

英文摘要

GERT networks have been widely applied in different domains.The parameters of GERTnetworks are usually determined by the decision makers' subjective opinions or experts'suggestions.It implies that the values of parameters in GERT networks are imprecise anduncertain.However,traditional GERT networks cannot reflect the characteristics ofreal-world network problems.To overcome the above weaknesses,this paper attempts touse fuzzy nunbers to represent the parameters' values,and than develops a Fuzzy GERTmodel.The developed fuzzy GERT model includes three procedures:(1)draw the GERTnetwork based on system analysis,(2)use triangular fuzzy numbers to represent theparameters' values in the GERT network and(3)apply the operations of triangular fuzzynumbers to formulate the Fuzzy GERT model.To validate the proposed fuzzy GERTmodel,one numerical example based on an existing GERT network has been adopted.

主题分类 工程學 > 工程學總論
参考文献
  1. Chang, P. T.,E. S. Lee(1999).Fuzzy decision networks and deconvolution.Computers & Mathematics with Applications,37,53-63.
  2. Chen, Y. L.,D. Rinks,T. Kwei(1997).Critical path in an activity network with time constraints.European Journal of Operational Research,100,122-133.
  3. Cheng, C. H.(1994).Fuzzy consecutive-k-out-of-n: F system reliability.Microelectronics and Reliability,34,1910-1922.
  4. Cheng, C. H.(1996).Fuzzy repairable reliability-based on fuzzy GERT.Microelectronics and Reliability,36,1557-1563.
  5. Clayton, E. R.,L. J. Moore(1972).GERT vs. PERT.The Journal of System Management,22,11-19.
  6. Elmaghraby, S. E.(1964).An algebra for the analysis of generalized activity networks.Management Science,10,494-514.
  7. Gong, D.,J. Rowings(1995).Calculation of safe float use in risk-analysis-oriented network scheduling.International Journal of Project Management,13,187-194.
  8. Italcura, H.,Y., Nishikawa(1984).Fuzzy network technique for technological forecasting.Fuzzy Sets and Systems,14,99-113.
  9. Kurihara, K.,N. Nishiuchi(2002).Efficient Monte Carlo simulation method of GERT-type network for project management.Computers and Industrial Engineering,42,521-531.
  10. Phillips, D. T.,A. Garcia-Diaz(1981).Fundamentals of Network Analysis.
  11. Pritsker, A. A. B.,G. E. Whitehouse(1996).GERT: graphical evaluation and review technique: part Ⅱ, probabilistic and industrial engineering application.The Journal of Industrial Engineering,17,293-301.
  12. Pritsker, A. A. B.,W. W. Happ(1966).GERT: graphical evaluation and review technique: part I fundamental.The Journal of Industrial Engineering,17,267-274.
  13. Ross, T. J.(1997).Fuzzy Logic with Engineering Applications.
  14. Shimoda, M.(2002).A natural interpretation of fuzzy sets and fuzzy relations.Fuzzy Sets and Systems,128,135-147.
  15. Wieckowski, A.(2002).Principles of the NNM method applied in the analysis of process realization.Automation in Construction,2,409-420.
  16. Wieckowski, A.,Zadeh, L. A.(1965).Fuzzy sets.Information and Control,8,338-353.
  17. 林玉彬(1993)。淡江大學管理科學研究所。
  18. 劉恩達(1992)。淡江大學管理科學研究所。
  19. 羅新興(1991)。國防管理學院資源管理研究所。
被引用次数
  1. (2013).Applying cost-reliability analysis to improve system reliability.工業工程學刊,30(7),467-472.