题名

Project Reliability Evaluation of a Restaurant under Time Constraints and Customer Demands

DOI

10.6186/IJIMS.2015.26.4.1

作者

Yi-Kuei Lin;Sheng-Chiang Chen;Kai-Jen Hsueh

关键词

Project network ; project reliability ; restaurant ; duration distribution ; work breakdown structure

期刊名称

International Journal of Information and Management Sciences

卷期/出版年月

26卷4期(2015 / 12 / 01)

页次

323 - 340

内容语文

英文

英文摘要

Every restaurant strives to maintain the quality of its service while simultaneously attracting new customers. Thus, restaurant managers face the dual challenges of adhering to time constraints and fulfilling customer demands. To investigate this issue in the present study, cooking was regarded as a project and was analyzed using a work breakdown structure. Since many real-world projects can be described by network models using arcs and nodes, we also evaluated restaurant performance by analyzing its project network. In general, a project network mainly consists of activities, and in this case, the capacity of each cooking appliance and the duration of each activity involved in the cooking process were also accounted for in the calculations. The main purpose of this study was to evaluate the project reliability, the probability that a restaurant can produce a demanded number of meals within a certain time. A restaurant multistate project network (RMPN) was constructed based on information provided by a restaurant about the cooking process. We then measured the time spent on each activity to generate the duration distribution. An algorithm was subsequently developed to assess the project reliability of the RMPN. This algorithm can be used by restaurant managers to assess the service qualities of their restaurants.

主题分类 基礎與應用科學 > 資訊科學
社會科學 > 管理學
参考文献
  1. Aggarwal, K. K.,Chopra, Y. C.,Bajwa, J. S.(1982).Capacity consideration inreliability analysis of communication systems.IEEE Transaction Reliability,31(2),177-180.
  2. Aven, T.(1985).Reliability evaluation of multistate systems with component.IEEE Transaction Reliability,34,473-479.
  3. Bendavid, I.,Golany, B.(2011).Predetermined intervals for start times of activities in the stochastic project scheduling problem.Annals of Operations Research,186,429-442.
  4. Bruni, M. E.,Guerriero, F.,Pinto, E.(2009).Evaluating project completion time in project networks with discrete random activity durations.Computers and Operations Research,36,2716-2722.
  5. Cheng, C. C.,Chen, C. T.,Hsu, F. S.,Hu, H. Y.(2012).Enhancing service quality im-provement strategies of fine-dining restaurants: new insights from integrating a two-phase decision-making model of IPGA and DEMATEL analysis.International Journal of Hospitality Management,31(4),11551166.
  6. Clancy, D. P.,Gross, G.,Wu, F. F.(1983).Probability flows for reliability evaluation of mul-tiarea power system interconnections.International Journal of Electrical Power & Energy Systems,5(2),100-114.
  7. Gido, J.,Clements, J. P.(1999).Successful Project Management.Ohio:South-western College Publishing.
  8. Golenko-Ginzburg, D.,Gonik, A.(1997).Stochastic network project scheduling with non-consumable limited resources.International Journal of Production Economics,48,29-37.
  9. Griffith, W. S.(1980).Multistate reliability models.Journal of Applied Probability,17,735-744.
  10. Ha, J.,Jang, S. C. S.(2010).Effects of service quality and food quality: the moderating role of atmospherics in an ethnic restaurant segment.International Journal of Hospitality Management,29,520529.
  11. Harold, K.(2009).Project Management A Systems Approach to Planning, Scheduling, and Controlling.NJ:John Wiley & Sons, Inc..
  12. Hiller, F. S.,Liberman, G. J.(2005).Introduction to Operations Research 8/e.NY:McGraw-Hill.
  13. Hsieh, C. C.,Chen, Y. T.(2005).Reliable and economic resource allocation in an unreliable flow network.Computer and Operations Research,32,613-628.
  14. Hsieh, C. C.,Chen, Y. T.(2005).Resource allocation decisions under various demands and cost requirements in an unreliable flow network.Computer and Operations Research,32,2771-2784.
  15. Hsieh, C. C.,Lin, M. H.(2006).Simple algorithms for updating multi-resource allocations in an unreliable flow network.Computers and Industrial Engineering,50,120-129.
  16. Jane, C. C.,Laih, Y. W.(2008).A practical algorithm for computing multi-state two-terminal reliability.IEEE Transactions on Reliability,57,295-302.
  17. Jane, C. C.,Lin, J. S.,Yuan, J.(1993).On reliability evaluation of a limited-flow network in terms of minimal cut sets.IEEE Transacts on Reliability,42,354-361.
  18. Jung J. M.,Sydnor S.,Lee S. K.,Almanza B.(2015).A conflict of choice: How consumers choose where to go for dinner.International Journal of Hospitality Management,45,88-98.
  19. Ke, H.,Liu, B.(2005).Project scheduling problem with stochastic activity duration times.Applied Mathematics and Computation,168,342-353.
  20. Klerides, E.,Hadjiconstantinou, E.(2010).A decomposition-based stochastic programming ap-proach for the project scheduling problem under time/cost trade-off settings and uncertain durations.Computers and Operations Research,37,2131-2140.
  21. Lee, H. E.(2015).Does a server's attentiveness matter? Understanding intercultural service encoun-ters in restaurants.International Journal of Hospitality Management,50,134-144.
  22. Lin, J. S.,Jane, C. C.,Yuan, J.(1995).On reliability evaluation of a capacitated-flow network in terms of minimal pathsets.Networks,25,131-138.
  23. Lin, Y. K.(2004).Reliability of a stochastic-flow network with unreliable branches and nodes under budget constraints.IEEE Transacts on Reliability,53,381-387.
  24. Lin, Y. K.(2008).Project management for arbitrary random durations and cost attributes by applying network approaches.Computers and Mathematics with Applications,56,2650-2655.
  25. Lin, Y. K.(2002).Using minimal cuts to evaluate the system reliability of a stochastic-flow network with failures at nodes and arcs.Reliability Engineering and System Safety,75,41-46.
  26. Lin, Y. K.(2007).On a multicommodity stochastic-flow network with unreliable nodes subject to budget constraint.European Journal of Operational Research,176,347-360.
  27. Lin, Y. K.(2001).A simple algorithm for reliability evaluation of a stochastic-flow network with node failure.Computer and Operations Research,28,1277-1285.
  28. Lin, Y. K.(2001).Study on the multicommodity reliability of a capacitated-flow network.Computers and Mathematics with Applications,42,255-264.
  29. Lin, Y. K.,Chang, P. C.,Fiondella, L.(2012).A study of correlated failures on the network reli-ability of power transmission systems.International Journal of Electrical Power & Energy Systems,43,954-960.
  30. Lin, Y. K.,Yeh, C. T.(2011).Maximal network reliability with optimal transmission line assignment for stochastic electric power network via genetic algorithms.Applied Soft Computing,11,2714-2724.
  31. Lin, Y. K.,Yeh, C. T.(2011).Reliability optimization of component assignment problem for a multistate network in terms of minimal cuts.Journal of Industrial and Management Optimization,7,211-227.
  32. Lin, Y. K.,Yeh, C. T.(2011).Computer network reliability optimization under double-resource assignments subject to a transmission budget.Information Sciences,181,582-599.
  33. Liu, J. Y.(2012).Schedule uncertainty control: A literature review.Physics Procedia,33,1842-1848.
  34. Liu, Q.,Zhao, Q.,Zang, W.(2008).Study on multi-objective optimization of flow allocation in a multi-commodity stochastic-flow network with unreliable nodes.Journal of Applied Mathematics and Computing,28,185-198.
  35. Liu, Y.,Jang, S.(2009).Perceptions of Chinese restaurants in the U.S.: What affects customer satisfaction and behavioral intentions?.International Journal of Hospitality Management,28,338-348.
  36. Pontrandolfo, P.(2000).Project duration in stochastic networks by the PERT-path technique.International Journal of Project Management,18,215-222.
  37. Sularto, L.,Wardoyo, Yunitasari T.(2015).User requirements analysis for restaurant POS and accounting application using quality function deployment.Procedia -Social and Behavioral Sciences,169,266-280.
  38. Symons M.(2013).The rise of the restaurant and the fate of hospitality.International Journal of Contemporary Hospitality Management,25,247-263.
  39. Wiesemann, W.,Kuhn, D.,Rustem, B.(2010).Maximizing the net present value of a project under uncertainty.European Journal of Operational Research,202,356-367.
  40. Xiao, B.,Yang, W.(2010).A revenue management model for products with two capacity dimensions.European Journal of Operational Research,205,412-421.
  41. Yeh, W. C.(2004).Multistate network reliability evaluation under the maintenance cost constraint.International Journal of Production Economics,88,73-83.
  42. Yeh, W. C.(2011).An improved method for multistate flow network reliability with unreliable nodes and a budget constraint based on path set.IEEE Transacts on Systems, Man, and Cybernetics Part A: Systems and Humans,41,350-355.
  43. Yeh, W. C.(2001).A simple algorithm to search for all d-MPs with unreliable nodes.Reliability Engineering and System Safety,73,49-54.
  44. Zuo, M. J.,Tian, Z.,Huang, H. Z.(2007).An efficient method for reliability evaluation of multistate networks given all minimal path vectors.IIE Transactions,39,811-817.