题名

Discount Strategies Investigation in Integrated Project Scheduling and Material Procurement

DOI

10.6186/IJIMS.2017.28.2.1

作者

B. H. Tabrizi;S. F. Ghaderi;S. Haji-Yakhchali

关键词

Project scheduling ; material purchasing ; Taguchi method ; genetic algorithm

期刊名称

International Journal of Information and Management Sciences

卷期/出版年月

28卷2期(2017 / 06 / 01)

页次

67 - 82

内容语文

英文

中文摘要

On-time materials readiness on the sites plays a remarkable role in successful execution of projects. Hence, this paper has addressed concurrent formulation of project scheduling and material procurement by a mixed-integer programming model, aiming to minimize penalty/reward to deliver the project and material holding, ordering, and purchasing costs, respectively. Both all-units and incremental discount approaches are applied here to consider more real purchasing states. A genetic algorithm is used to solve the problems with large sizes, in particular, whose underlying factors are calibrated by the Taguchi method. Finally, the applicability and efficiency of the mathematical model is tested by a set of size-categorized instances.

主题分类 基礎與應用科學 > 資訊科學
社會科學 > 管理學
参考文献
  1. Liang, W.Y.,Huang, C.C.(2013).The genetic algorithm with rough set theory incorporated into the patent composition.International Journal of Information and Management Sciences,24,39-55.
    連結:
  2. Zhang, W. X.,Zhang, H. H.(2013).Task Assignment Optimization for the Batch Casualty Surgeries in Emergencies based on Extended Genetic Algorithm.International Journal of Information and Management Sciences,24,117-129.
    連結:
  3. Aquilano, N.J.,Smith, D.E.(1980).A formal set of algorithms for project scheduling with critical path method-material requirements planning.Journal of Operations Management,1,57-67.
  4. Bruni, M.E.,Beraldi, P.,Guerriero, F.,Pinto, E.(2011).A heuristic approach for resource constrained project scheduling with uncertain activity durations.Computers & Operations Research,38,1305-1318.
  5. Chen, S.M.,Griffis, F. H.,Chen, P. H.,Chang, L.M.(2012).Simulation and analytical techniques for construction resource planning and scheduling.Automation in Construction,21,99-113.
  6. Dodin, B.,Elimam, A. A.(2001).Integrated project scheduling and material planning with variable activity duration and rewards.IIE Transactions,33,1005-1018.
  7. Dodin, B.,Elimam, A. A.(2008).Integration of equipment planning and project scheduling.European Journal of Operational Research,184(3),962-980.
  8. Drezet, L. E.,Billaut, J. C.(2008).A project scheduling problem with labour constraints and time-dependent activities requirements.International Journal of Production Economics,112,217-225.
  9. Erbasi, A.,Sepil, C.(1999).A modified heuristic procedure for materials management in project networks.International Journal of Industrial Engineering-Theory,6,132-140.
  10. Fu, F.(2014).Integrated scheduling and batch ordering for construction project.Applied Mathemat- ical Modelling,38,784-797.
  11. Holland, J.(1975).Adaptation in natural and artificial systems.Ann Arbor:University of Michigan Press.
  12. Kethley, R. B.(2008).Using Taguchi Loss Functions to develop a single objective function in a multi-criteria context: A scheduling example.International Journal of Information and Management Sciences,19,589-600.
  13. Kolisch, R.(1996).Serial and parallel resource-constrained project scheduling methods revisited: theory and computation.European Journal of Operational Research,90,320-333.
  14. Kyriakidis, T. S.,Kopanos, G. M.,Georgiadis, M. C.(2012).MILP formulations for singleand multi-mode resource-constrained project scheduling problems.Computers and Chemical Engineering,36,369-385.
  15. Liu, S. S.,Wang, C. J.(2008).Resource-constrained construction project scheduling model for profit maximization considering cash flow.Automation in Construction,17,966-974.
  16. Liu, S.,Yung, K. L.,Ip, W. H.(2007).Genetic local search for resource-constrained project scheduling under uncertainty.International Journal of Information and Management Sciences,18,347-363.
  17. Long, L. D.,Ohsato, A.(2008).Fuzzy critical chain method for project scheduling under resource constraints and uncertainty.International Journal of Project Management,26,688-698.
  18. Lova, A.,Tormos, P.,Cervantes, M.,Barber, F.(2009).An efficient hybrid genetic algorithm for scheduling projects with resource constraints and multiple execution modes.International Journal of Production Economics,117,302-316.
  19. Lu, H. W.,Lu, Y. H.,Yang, H. M.(2009).Ordered categorical data in fuzzy ranking applied to service quality for western restaurants.International Journal of Information and Management Sciences,20,505-518.
  20. Maiti, M. K.,Maiti, M.(2009).Utilization of Multi-Objective Genetic Algorithm for one-item multi-level Inventory distribution system.International Journal of Information and Management Sciences,20,291-304.
  21. Schmitt, T.,Faaland, B.(2004).Scheduling recurrent construction.Naval Research Logistics,51,1102-1128.
  22. Sheikh Sajadieh, M.,Shadrokh, S.,Hassanzadeh, F.(2009).Concurrent Project Scheduling and Material Planning: A Genetic Algorithm Approach.Scientia Iranica- Transaction E: Industrial Engineering,16,91-99.
  23. Smith-Daniels, D. E.,Aquilano, N. J.(1984).Constrained resource project scheduling subject to material constraints.Journal of Operations Management,4,369-388.
  24. Smith-Daniels, D.E.,Smith-Daniels, V.L.(1987).Optimal project scheduling with materials or- dering.IIE Transactions,19,122-129.
  25. Taguchi, G.(1986).Introduction to quality engineering.White Plains:Asian Productivity Organi- zation/UNIPUB.
  26. Wuliang, P.,Chengen, W.(2009).A multi-mode resource-constrained discrete time-cost tradeoff problem and its genetic algorithm based solution.International Journal of Project Management,27,600-609.
  27. Yang, T.,Shen, Y.A.,Cho, C.,Lin, Y.R.(2012).The use of a simulation, a hybrid Taguchi and dual response surface methods in the automated material handling system tool-to-tool strategy for a 300-mm fab.European Journal of Industrial Engineering,6,281-300.