题名

DIFFERENT FINANCIAL ANALYSES ON BOT PROJECTS WITH THE CASE OF HUALIEN HOPING INDUSTRIAL HARBOR

DOI

10.6292/AFPF.2016.07.04

作者

Hong-Ching Su;Chia-Jung Tu;Tyrone T. Lin

关键词

Build-Operate-Transfer ; Net Present Value ; Internal Rate of Return ; Sensitivity Analysis ; Decision Tree ; Hualien Hoping Industrial Harbor

期刊名称

Advances in Financial Planning and Forecasting

卷期/出版年月

7期(2016 / 10 / 01)

页次

77 - 89

内容语文

英文

中文摘要

This study uses the Hoping Industrial Harbor build-operate-transfer (BOT) project as an example and analyzes the feasibility of financial investment projects. In traditional investment evaluation decisions, capital budgeting methods such as net present value (NPV) and internal rate of return (IRR) are most commonly used but traditional capital budgeting is a static model, which will not help decision-making in a timely manner in the face of the uncertain future cash flows. It also lacks management flexibility. Decision makers are assisted by using sensitivity analysis in consideration of the following variables: shipping volume, announced land, rate of government rent, and facility maintenance fees to make strategic decisions under a variety of future financial changes. Then, this study applies an expansion of scale decision tree to determine whether to implement a second phase project and provide decision makers more flexible investment strategies. The findings of this study contribute to the development of related future BOT projects.

主题分类 社會科學 > 經濟學
参考文献
  1. Chen, A.-L.,Hsiao, C.-H.,Kao, L.-F.,Lu, C.-S.(2011).The design of an optimal corporate governance system in Taiwan.Advances in Financial Planning and Forecasting,4,77-97.
    連結:
  2. Bakatjan, S.,Arikan, M.,Tiong, R. L. K.(2003).Optimal capital structure model for BOT power projects in Turkey.Journal of Construction Engineering and Management,129,89-97.
  3. Binder, J. J.,Chaput, J. S.(1996).A positive analysis of corporate capital budgeting practices.Review of Quantitative Finance and Accounting,6,245-257.
  4. Chen, B.,Liou, F.-M.,Huang, C.-P.(2012).Optimal financing mix of financially non-viable private-participation investment project with initial subsidy.Engineering Economics,23,452-461.
  5. Cheng, H.-K.(2010).Lessons learned from BOT infrastructure development in Taiwan: A case study of the Taiwan High Speed Railway (THSR) project.Public Administration Quarterly,34,51-75.
  6. Delen, D.,Kuzey, C.,Uyar, A.(2013).Measuring firm performance using financial ratios: A decision tree approach.Expert Systems with Applications,40,3970-3983.
  7. Dey, P. K.(2012).Project risk management using multiple criteria decision-making technique and decision tree analysis: A case study of Indian oil refinery.Production Planning & Control,23,903-921.
  8. Drury, C.,Tayles, M.(1996).UK capital budgeting practices: Some additional survey evidence.The European Journal of Finance,2,371-388.
  9. Duan, C. W.,Lin, W. T.,Lee, C. F.(2003).Sequential capital budgeting as real options: the case of a new DRAM chipmaker in Taiwan.Review of Pacific Basin Financial Markets and Policies,6,87-112.
  10. Gupta, A.,Gupta, M. C.,Agrawal, R.(2013).Identification and ranking of critical success factors for BOT projects in India.Management Research Review,36,1040-1060.
  11. Kumaraswamy, M. M.,Morris, D. A.(2002).Build-operate-transfertype procurement in Asian mega projects.Journal of Construction Engineering and Management,128,93-102.
  12. Kutkarni, N.,Prusty, A.(2007).Bidding strategy for BOT port terminal projects in India.The Journal of Structured Finance,12(4),90-106.
  13. Lee, K.-J.,Shyu, D. S.,Dai, M.-L.(2009).The valuation of information technology investments by real options analysis.Review of Pacific Basin Financial Markets and Policies,12,611-628.
  14. Liu, T.,Wilkinson, S.(2014).Large-scale public venue development and the application of Public-Private Partnerships (PPPs).International Journal of Project Management,32,88-100.
  15. Ock, J. H.,Han, S. H.,Park, H. K.,Diekmann, J. E.(2005).Improving decision quality: A risk-based go/no-go decision for build operate transfer (BOT) projects.Canadian Journal of Civil Engineering,32,517-532.
  16. Shen, L.,Lee, R. K.,Zhang, Z.(1996).Application of BOT system for infrastructure projects in China.Journal of Construction Engineering and Management,122,319-323.
  17. Yun, S.,Han, S. H.,Kim, H.,Ock, J. H.(2009).Capital structure optimization for build-operate-transfer (BOT) projects using a stochastic and multiobjective approach.Canadian Journal of Civil Engineering,36,777-790.
  18. Zhang, X.(2005).Financial viability analysis and capital structure optimization in privatized public infrastructure projects.Journal of Construction Engineering and Management,131,656-668.